Exercises 1-3

Project Time and Cost Exercises
PM/571 Project Management

Project Time and Cost Exercises
1. Mrs. Tolstoy and her husband, Serge, are planning their dream house. The lot for the house sits high on a hill with a beautiful view of the Appalachian Mountains. The plans show the size of the house to be 2,900 square feet. The average price for a lot and house similar to this one has been $120 per square foot. Fortunately, Serge is a retired plumber and feels he can save money by installing the plumbing himself. Mrs. Tolstoy feels she can take care of the interior decorating.
The following average cost information is available from a local bank that makes loans to local contractors and disperses progress payments to contractors when specific tasks are verified as complete.
24% Excavation and framing complete
8% Roof and fireplace complete
3% Wiring roughed in
6% Plumbing roughed in
5% Siding on
17% Windows, insulation, walks, plaster, and garage complete
9% Furnace installed
4% Plumbing fixtures installed
10% Exterior paint, light fixtures installed, finish hardware installed
6% Carpet and trim installed
4% Interior decorating
4% Floors laid and finished
 
a. What is the estimated cost for the Tolstoy's house if they use contractors to complete all of the house? $348,000.00.
b. Estimate what the cost of the house would be if the Tolstoy's use their talents to do some of the work themselves. The estimated cost of the house would be $313,200.00 which is a savings of $34,800.
2. Below is a project WBS with cost apportioned by percents. If the total project cost is estimated to be $600,000, what are the estimated costs for the following deliverables?
a. Design? $240,000
b. Programming? $120,000
c. In-house testing? $240,000
Exercise 5.3 WBS Figure

What weaknesses are inherent in this estimating approach? Weaknesses inherent in this estimating approach are that this approach requires sound, accurate historical data because if total cost...