PIG PENS PROJECT 2011

Received 169,000 from D.X.B. on 8/7/2011

  a) Paid house rent for the month of July 14,000/-

  b) Authorized Mato to take @ 10,000/-

  c) Authorized Cathy to take @ 10,000/-

  d) To cater for hospital bill @5,000/-

  e) Bought   used gate for modification later @ 20,000/- at New Kitusuru

  f) Bought used gate for @ 4,000

  g) Bought gate for pigs entrance @ 3,500/-

  h) Transport cost incurred for both gates from Ruai to Nakuru @ 5,810

  i) Bought a big water barrel for water at construction site @1,650/-

  j) Made   3,967 pieces home made blocks size 18x8 for the perimeter   wall for all six plots @5/- =19,835

  k) Bought 4,000ltrs of water @ 2,000/-

  l) Bought 6,200lts of water @ 2,800/-

  m) Bought 7,200lts of water @ 3,000/-



Sub total cost =101,595/-



Withdraw 100,000 on 06/08/2011

Received 225,329 on 11/9/2011



Authorized to deposit money to Co-op bank Ukulima branch =80,000/-



COST OF MATERIALS USED FOR THE PERIMETER WALL

    a) Bought 25 bags of cement @ 720 =18,000/-

    b) Bought sand at Mwariki pipeline 8tonnes @ 3000/- and cost of delivery @ 5,500=8,500/-

    c) Labour cost used for perimeter wall so far @46,500

    d) Polythene bags used as DPC for perimeter wall @1,000/-




        Sub total cost =154,000/-

PIG PENS CONSTRUCTION

  1. Excavation

Preparing field, uprooting trees and leveling the ground) for two days @ 500/-

2 kgs of nails 3”inches @ 360/-

1 kgs of 2 ½ “inches @130/-

Sisal rope @120/-

Offcuts 17pcs @55/- 900/-



      Sub total cost=2,010



  2. Foundation digging

Day one

Fundi Mwaura @ 800/-

4 casual labourers @1,800/-

Day two

2 casual labourers @ 600/-

Sub total=3,200



  3. Foundation settings

Day one

Fundi Njuguna (snr) @ 800/-

2 casual labourers @ 250 =500/-

4 bags of cement @720=2880

Day two

Fundi Njuguna (snr) @800/-

2 casual labourers @250 =500/-

Fundi Karis @500

1 casual @ 100/-

Day three

Fundi Karis @ 500/-

Fundi Muya @500/-...